How to build a college football field in 8 days
Bristol Motor Speedway plans to transform the legendary Speedway into the world’s largest football stadium for the inauguralĀ āBattle at Bristol, College Football’s Biggest EVER”Ā game to be held onĀ Sept. 10, 2016. The event willĀ feature a border battle between the Virginia Tech Hokies andĀ Tennessee VolunteersĀ and is projected to set the NCAA record for highest single-game attendance.
With an estimated seating capacity of 150,000, theĀ Battle atĀ BristolĀ is on track to crush prior college football attendance records. The previous two largest-attended college football games drew an estimated 120,000 and 115,000 fans.
“There has always been a desire by fans to see a football game at our historic Speedway,” saidĀ Bruton Smith, chairman and CEO of Speedway Motorsports. “We couldn’t be more excited to turn this long-time rumor into a reality and to provide sports fans with an unforgettable, once-in-a-lifetime opportunity to be a part of the biggest college football game ever.”

A proposed rendering of Bristol Motor Speedway set-up for the “Battle at Bristol” college football game between Virginia Tech and Tennessee on Sept. 10, 2013. (PRNewsFoto/Bristol Motor Speedway)
Over the course of a few weeks, the Speedway will transform from an iconic short track to a world-class football field. Key facts about the transformation include:
- Immediately following theĀ August 2016Ā NASCAR race at Bristol Motor Speedway, approximately 400 workers will immediately begin bulk cleaning, and then detailing, the Speedway.
- An estimated 10-12 crews will begin pressure washing ā a process that is normally done in February prior to the March NASCAR weekend.
- Separate crews will clean all suites in seven days ā a process that normally takes four-to-six weeks.
- Turf and field build will be completed in eight days.
- Approximately 8,500 tons of rock will be used to build the base of the field.
- The rock will be brought in by approximately 400 truckloads. The complete haul-in process will take three, 10-12 hour days.
- The base rock will be 3 feet 6 inches deep in the middle of the infield tapering to one and a half feet on sidelines to create the proper sloping effect for drainage.